July 1999 |
Scoping study team established at IIED Richard Sandbrook |
|||||
|
|
||||||
| August - September 1999 |
Scoping Report underway |
|||||
|
|
||||||
|
October 1999 |
Scoping Report completed Scoping Report. |
|
||||
|
|
||||||
| December 1999 |
Scoping Report approved by the World Business Council for Sustainable Development WBCSD. |
|||||
|
|
||||||
| January 2000 |
Dissemination of Scoping Report |
|||||
|
|
||||||
| February 2000 |
Director search Regional visit by Project Co-ordinator, Richard Sandbrook, to Australia |
|||||
|
|
||||||
| March 2000 |
Planning intensifies and first Project Bulletin published Project strategy. |
|
||||
|
|
||||||
| April 2000 |
Appointments: Project Director and Project Co-ordinator visit Southern Africa |
|||||
|
|
||||||
| May 2000 |
May 5-6 Strategic Planning Workshop (London, England) |
|||||
|
Meeting notes, agenda, and List of workshop participants.
|
||||||
|
What is the Role of MMSD? presentations by |
||||||
|
The Research Horizon: A first View at 30,000ft - a paper presented by Nick Robins.
|
||||||
|
Implementation and Outputs: Turning Words into Action - a presentation by Luke Danielson.
|
||||||
|
|
||||||
| 22-23 May 2000 | First meeting of the Assurance Group (London, England) | |||||
|
Agenda. |
||||||
|
Fitting the Process Together - a presentation by Luke Danielson. |
||||||
|
Analysis for Change: Understanding the Status Quo, Drivers and Impediments to Change - a paper by Nick Robins. |
||||||
|
Strategic Planning Workshop: Feedback - a presentation by Elisabeth Wood. |
||||||
|
Communications: Public Relations and Media Strategy - a presentation by Lilian Chatterjee, IIED Communications Director. |
||||||
|
Outcomes - a presentation by Luke Danielson. |
||||||
|
Topics for Analysis presented by Luke Danielson. |
||||||
|
Memo on Sponsors Group prepared by Richard Sandbrook. |
||||||
|
Profile of Assurance Group members. |
||||||
|
Memo on Assurance Group prepared by Richard Sandbrook. |
||||||
|
Minutes Assurance Group Minutes. |
||||||
|
|
||||||
| June 2000 |
Project Administrator starts work Sarah Henson Project Personal Assistant starts work Lucy Brain-Gabbott |
|||||
|
|
||||||
| July 2000 |
Appointments: Communications coordinator and research fellows |
|||||
|
Meeting on preparing for implementation |
||||||
|
Focus on regional partnership building |
||||||
|
Consultation document |
||||||
|
MMSD project Director and Project Coordinator visit the USA |
||||||
|
|
||||||
| August 2000 |
Appointments: Coordinator Stakeholder Engagement, Research Manager, Research
Fellow |
|||||
|
Meeting in South Africa to discuss Regional Process |
||||||
|
Meetings with North American stakeholders in Denver, Colorado, Aug 24-25 |
||||||
|
28-29 August |
||||||
|
|
||||||
| September 2000 |
Visit by Project Director and Coordinator for Stakeholder Engagement to Indonesia, Philippines, Australia and other countries in the region |
|||||
|
VISIT TO MANILA. |
![]() |
|||||
|
|
||||||
| October 2000 |
Appointment: Research Fellow Juan Velasquez |
|||||
|
Proposed Outline for Draft Report. |
||||||
|
Guidelines for Forming Regional Partnerships. |
||||||
|
13 October |
||||||
|
Sponsors Group Meeting. |
||||||
|
MMSD: A Six Month Report - Presentation by Luke Danielson. |
||||||
|
An MMSD Briefing Paper. |
||||||
|
A Guide to MMSD. |
||||||
|
Draft Work Plan - 1 October 2000. |
||||||
|
Luke Danielson in Prague for ICEM World Conference. |
MMSD Report to the ICEM World Conference (powerpoint document) |
|||||
|
|
||||||
| November 2000 |
Appointment: Report Coordinator Ben Sandbrook |
|||||
|
7-10 November |
||||||
|
16-17 November |
||||||
|
30 November - 1 December |
||||||
|
|
||||||
|
December 2000 |
Appointment: Assistant Project Coordinator Bernice
Lee |
|||||
|
5 December |
||||||
|
8 December |
||||||
|
11 December |
||||||
|
12 December |
||||||
|
|
||||||
| January 2001 |
Appointments: Communications and External Relations Executive, Administrative
Assistant and Research Fellow |
|||||
|
10, 12 January Washington, DC, USA |
||||||
|
22-23 January |
||||||
|
|
||||||
| February 2001 |
15 February |
|||||
|
|
||||||
| March 2001 |
8-9 March |
|||||
|
11-14 March |
||||||
|
14 March |
|
|||||
|
25 March - 3 April |
||||||
|
|
||||||
| April 2001 |
4-6 April |
|||||
|
9 April |
|
|||||
|
20 April |
||||||
|
23-24 April |
|
|||||
|
23 April |
||||||
|
26 April |
||||||
|
|
||||||
| May 2001 |
4-5 May |
For further information, see our Regional Partners page. |
||||
|
7 - 8 May |
Address from The Honourable Phumzile Mlambo-Ngcuka, Minister of Minerals and Energy of South Africa. |
|||||
|
14-16
May |
||||||
|
25-27 May |
Luke
Danielson presentation |
|||||
|
|
||||||
|
June 2001 |
7 June |
|||||
|
11-12 June |
For more information, see our Mining and Biodiversity page |
|||||
|
27 June |
||||||
|
|
||||||
| July 2001 |
Appointment: Project Assistant Andrea
Steel |
|||||
|
11 July |
|
|||||
|
14-18 July |
For more information, see our Large Volume Waste page. |
|||||
|
18 July |
||||||
|
19 July |
||||||
|
27 July |
|
|||||
|
|
||||||
| August 2001 |
Appointment: Editorial Research Assistant Bruce
Howard |
|||||
|
9-10 August |
|
|||||
|
15-17 August |
|
|||||
|
23-24 August |
|
|||||
|
|
||||||
| September 2001 |
6 September |
|
||||
|
7 September |
|
|||||
|
10 September |
|
|||||
|
13-14 September |
|
|||||
|
18-19 September |
|
|||||
|
25-28 September |
||||||
|
28-29 September |
||||||
|
|
||||||
|
October 2001 |
Appointment: Research Fellow Juan-Carlos
Altamirano |
|||||
|
8-11 October |
||||||
|
15-16 October |
|
|||||
|
25-26 October |
|
|||||
|
|
||||||
| November 2001 |
12-13 November |
|||||
|
19-20 November |
|
|||||
|
21-26 November |
|
|||||
|
28 November |
|
|||||
|
29-30 November |
|
|||||
|
|
||||||
| December 2001 |
3-5 December |
|
||||
|
|
||||||
| January 2002 |
14-15 January |
|
||||
| |
||||||
| February 2002 |
4-6 February |
|||||
|
18-19 February |
|
|||||
|
|
||||||
| March 2002 |
4 March |
|
||||
|
5-6 March |
|
|||||
|
10-13 March |
||||||
|
12-15 March |
||||||
|
18-20 March |
||||||
|
22 March |
||||||
|
25 March - 1 April |
||||||
|
|
||||||
| April 2002 |
2-3 April |
|||||
|
10 April |
||||||
|
|
||||||
| May 2002 |
1
May |
|
||||
|
12-15 May |
||||||
|
|
||||||
| June 2002 | ||||||
|
|
||||||
| July 2002 |
Full published version of MMSD Report available |
For further details click here. |
||||
|
|
||||||
| August 2002 |
26
August - 4 Septembe 30 August |
|||||
|
|
||||||
|
September 2002 |
MMSD Project Signs
Off Project offices closed |
To read a sign-off message from MMSD Project Coordinator Richard Sandbrook click here. | ||||
|